Dam Update!

In case you missed the last Homeowners Association meeting, here is the latest happenings on the dam and lake:

Because of the weather and equipment and other projects, they are running about a month behind schedule. The broke through the concrete at the end of the spillway, but there were two layers (so more work than anticipated). The old pipe was filled and is no longer draining, and they will be digging to put in a new pipe soon. Dry soil is needed in the lake bed to build the new structure with the siphon - once complete the lake level will be about 9 feet (will go over from time to time). We are planning to move a dock to the mound toward the center of the lake, so that once the project is complete it will be farther out from the shore. We would love to make a track around the lake for running, but we would need to raise funds to make something like that happen in the future.